Roads16PJ0029

CONSTRUCTION/IMPROVEMENT/REHABILITATION OF BARANGAY DOLOWOG FMR

CONSTRUCTION/IMPROVEMENT/REHABILITATION OF BARANGAY DOLOWOG FMR is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱1,977,067.24. Status: Reported complete (DPWH). Contractor on record: LUCKY A CONST CORP. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-16-0038385

₱343,000.00 · FY2016

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,977,067.24

Progress

Reported complete (DPWH)

Start Date

May 29, 2016

Target End

July 27, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.