Roads18OG0067

WIDENING OF B. SERRANO AVENUE, QUEZON CITY

WIDENING OF B. SERRANO AVENUE, QUEZON CITY is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱35,306,885.16. Status: Past target date (DPWH On-Going). Contractor on record: KAIRO KONSTRAK INC. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement/Rehabilitation of San Juan River, Quezon City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-18-0027828

₱222,000.00 · FY2018

Released to Cagayan de Oro City 1st re District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

15 projects · ₱636.2M total · 0 flags

4. Implementation

Contract Amount

₱35,306,885.16

Progress

Past target date (DPWH On-Going)

Start Date

May 17, 2018

Target End

July 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.