GAA 2025 OO-225LG0017

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MAYO RIVER, PHASE I, MATI CITY, DAVAO ORIENTAL

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MAYO RIVER, PHASE I, MATI CITY, DAVAO ORIENTAL is a DPWH-tracked public work in Davao Oriental 2nd DEO, Region XI. Reported contract value: ₱114,641,972.71. Status: Past target date (DPWH On-Going). Contractor on record: MAER SUMMIT KONSTRUKT CO. Figures trace to dpwh.

Davao Oriental 2nd DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Package 4, Mati City, Davao Oriental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-25-0004117

₱181,000.00 · FY2025

Released to Vito National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱114,641,972.71

Progress

Past target date (DPWH On-Going)

Start Date

May 20, 2025

Target End

July 16, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.