Buildings and Facilities16GB0247

CONSTRUCTION OF 2-UNITS 2 STOREY TEN(10) CLASSROOM SCHOOL BUILDING AT MOSCOSO-RIOS NHS, HAMTIC, ANTI

CONSTRUCTION OF 2-UNITS 2 STOREY TEN(10) CLASSROOM SCHOOL BUILDING AT MOSCOSO-RIOS NHS, HAMTIC, ANTI is a DPWH-tracked public work in Antique DEO, Region VI. Reported contract value: ₱25,131,306.82. Status: Reported complete (DPWH). Contractor on record: LAK-K BUILDERS CO. Figures trace to dpwh.

Antique DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱25,131,306.82

Progress

Reported complete (DPWH)

Start Date

September 28, 2017

Target End

June 16, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.