Roads23BG0133

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONCRETING OF BARANGAY ROAD,BRGY. STO. TOMAS-BAGNOS (TRAMO), ALICIA, ISABELA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONCRETING OF BARANGAY ROAD,BRGY. STO. TOMAS-BAGNOS (TRAMO), ALICIA, ISABELA is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱4,877,285.41. Status: Reported complete (DPWH). Contractor on record: ACCELERATED METAL TECHNOLOGY. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction River Flood Control Project along Ganano River Bank, barangay Apanay, Alicia, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-23-0022537

₱0.00 · FY2023

Released to 0300008 Regional Office VIII - - (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,877,285.41

Progress

Reported complete (DPWH)

Start Date

May 17, 2023

Target End

June 19, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.