Bridges21EA0119

COMPLETION OF PULONG PARANG BRIDGE AND APPROACHES, SANTA CRUZ, MARINDUQUE

COMPLETION OF PULONG PARANG BRIDGE AND APPROACHES, SANTA CRUZ, MARINDUQUE is a DPWH-tracked public work in Marinduque DEO, Region IV-B. Reported contract value: ₱24,499,560.78. Status: Reported complete (DPWH). Contractor on record: ZUIDEN BUILDERS INC. Figures trace to dpwh.

Marinduque DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Matalaba Flood Control, Sta. Cruz, Marinduque
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-21-0001582

₱3,890,000.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱24,499,560.78

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

December 29, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.