GAA 2024 DepEd BEFF24IK0103

PHASE1 CONSTRUCTION OF MODIFIED DESIGN W/ PARAPET, 1-UNIT, 4-STOREY, 20-CL SCHOOL BLDG. IN CATBALOGAN II CENTRAL ELEM. SCHOOL, BARANGAY POBLACION 7, CATBALOGAN CITY, SAMAR

PHASE1 CONSTRUCTION OF MODIFIED DESIGN W/ PARAPET, 1-UNIT, 4-STOREY, 20-CL SCHOOL BLDG. IN CATBALOGAN II CENTRAL ELEM. SCHOOL, BARANGAY POBLACION 7, CATBALOGAN CITY, SAMAR is a DPWH-tracked public work in Samar 2nd DEO, Region VIII. Reported contract value: ₱39,795,816.46. Status: Past target date (DPWH On-Going). Contractor on record: PYUKEI CONST INC. Figures trace to dpwh.

Samar 2nd DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱10,000

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-B-24-0001361 · ₱20,212,000

    Possible match · score 0.59

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    38% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Cagutsan, Catbalogan City, Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-B-24-0001361

₱20,212,000.00 · FY2024

Released to Samar 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱39,795,816.46

Progress

Past target date (DPWH On-Going)

Start Date

March 5, 2025

Target End

October 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.