Roads15HH0127

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, CEBU BALAMBAN TRANSCENTRAL HIGHWAY (S00031CB), K0014+500-K0015+640, K0017+200-K0018+00, K0021+300-K0023+800, CEBU CITY

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, CEBU BALAMBAN TRANSCENTRAL HIGHWAY (S00031CB), K0014+500-K0015+640, K0017+200-K0018+00, K0021+300-K0023+800, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱26,068,132.83. Status: Reported complete (DPWH). Contractor on record: PLD CONST AND DEVELOPMENT INC FORMERLY: PLD CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2016 · ₱25,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-D-16-0033206 · ₱3,766,106 · release to the district office, not itemized per project

    Possible match · score 0.63

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱26,068,133 · PLD CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-05-15 → 2025-01-18

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, CEBU BALAMBAN TRANSCENTRAL HIGHWAY (S00031CB), K0014+500-K0015+640, K0017+200-K0018+00, K0021+300-K0023+800, CEBU CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Flood Control and Drainage System along P. Lopez - Colon - A. Borromeo, Brgy. Ermita, Cebu City
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-16-0033206

₱3,766,106.00 · FY2016

Released to Supreme Court of the Philippines and the Lower (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Off - Carriageway Improvement including Drainage,

₱26,068,132.83 · PLD CONSTRUCTION

Award / contract ref: 15HH0127

Contractor

A

230 projects · ₱5.3B total · 0 flags

Other projects by this contractor

CONST. OF FLOOD CONTROL STRUCTURE ALONG MARANDING RIVER, INCL. ROW, PACKAGE 6, LANAO DEL NORTE

Region X, Region X

2024₱157.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE FACILITY (LABANGON PUBLIC MARKET), BRGY. LABANGON, CEBU CITY, CEBU

Region VII, Region VII

2023₱140.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (LANAO CULTURAL CENTER), KAPATAGAN NATIONAL HIGH SCHOOL, BARANGAY POBLACION, KAPATAGAN, LANO DEL NORTE

Lanao del Norte 2nd DEO, Region X

2022₱118.2M
Reported complete (DPWH)
No sat.

CLUSTER G PREVENTIVE MAINTENANCE OF VARIOUS ROAD PROJECTS IN LANAO DEL NORTE1) MALABANG-DOBLESTON-TUKURAN RD - K1974 + 000 - K1975 + 300 =PHP62,465,415.002) MALABANG-DOBLESTON-TUKURAN RD - K1975 + 300 - K1977 + 560

Region X, Region X

2024₱114.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS, N. BACALSO AVE (CEBU SOUTH RD) - K0111+006.00 - K0111+912.00 AND K0113+905.00 - K0114+433.00

Cebu 2nd DEO, Region VII

2023₱98.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

PREVENTIVE MAINTENANCE ALONG LINAMON-ZAMBOANGA ROAD K1550+334-K1552+981, BACOLOD, LANAO DEL NORTE

Lanao del Norte 1st DEO, Region X

2021₱96.5M
Reported complete (DPWH)
View all 230 projects →

4. Implementation

Contract Amount

₱26,068,132.83

Progress

Reported complete (DPWH)

Start Date

February 24, 2016

Target End

June 4, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Cite this record

Love the Philippines. “OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, CEBU BALAMBAN TRANSCENTRAL HIGHWAY (S00031CB), K0014+500-K0015+640, K0017+200-K0018+00, K0021+300-K0023+800, CEBU CITY.” Source: DPWH. Data as of October 21, 2026. https://lovethephilippines.com/projects/309237d3-f047-42c0-bec9-820e25c09799

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)City of CebuMalubog
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
LandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.