Roads15KI0065

ROAD UPGRADING (GRAVEL TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARD (HDM-4 PROJECT ANALYSIS INTERMITTENT SECTIONS, NATL SECONDARY, OROQ.CITY - CALAMBA MT. ROAD, MISAMIS OCCIDENTAL, K1768+624 - K1769+540

ROAD UPGRADING (GRAVEL TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARD (HDM-4 PROJECT ANALYSIS INTERMITTENT SECTIONS, NATL SECONDARY, OROQ.CITY - CALAMBA MT. ROAD, MISAMIS OCCIDENTAL, K1768+624 - K1769+540 is a DPWH-tracked public work in Misamis Occidental 1st DEO, Region X. Reported contract value: ₱29,500,320.40. Status: Reported complete (DPWH). Contractor on record: L C CONST CORP FOR: L C CONST. Figures trace to dpwh.

Misamis Occidental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control - Revetment along the proposed Corazon Aquino Road Extension, Oroquieta, Misamis Occidental
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0001091

₱98,182.00 · FY2016

Released to Eastern Samar National Comprehensive High SchTer (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

94 projects · ₱1.2B total · 0 flags

4. Implementation

Contract Amount

₱29,500,320.40

Progress

Reported complete (DPWH)

Start Date

February 18, 2016

Target End

August 9, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.