Buildings and Facilities19FB0141

LOCAL PROGRAM: CONSTRUCTION OF BARANGAY PERMANENT EVACUATION HOLDING CENTER, BRGY. CABACONGAN, MANITO, ALBAY

LOCAL PROGRAM: CONSTRUCTION OF BARANGAY PERMANENT EVACUATION HOLDING CENTER, BRGY. CABACONGAN, MANITO, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱4,837,968.00. Status: Reported complete (DPWH). Contractor on record: QDC CONST AND SUPPLY. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    NCA NCA-ROXI-19-0019722 · ₱241,576 · release to the district office, not itemized per project

    Possible match · score 0.70

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19FB0141 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-12-09 → 2014-12-09

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: LOCAL PROGRAM: CONSTRUCTION OF BARANGAY PERMANENT EVACUATION HOLDING CENTER, BRGY. CABACONGAN, MANITO, ALBAY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-19-0019722

₱241,576.00 · FY2019

Released to Division of Davao del Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

50 projects · ₱417.1M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINTENANCE -PRIMARY ROADS - MAHARLIKA HIGHWAY - K0524+188-K0524+481, K0526+000-K0526+522, DARAGA, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2025₱29.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239-PREVENTIVE MAINTENANCE-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0528+460-K0528+771, K0539+000-K0539+285.5, DARAGA, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2025₱27.6M
Past target date (DPWH On-Going)
No sat.

CLUSTER 28-CONSTRUCTION OF RURAL HEALTH UNITS(RHU) AND BARANGAY HEALTH STATION (BHS) IN BACACAY AND MALILIPOT, ALBAY

Albay 1st DEO, Region V

2018₱22.1M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT COAST GUARD OF THE PHILIPPINES, REGIONAL SITE CENTER, RAWIS, LEGAZPI CITY

Albay 2nd DEO, Region V

2024₱19.0M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE-TERTIARY ROADS- COMUN-INARADO-PENAFRANCIA RD - K0522 + 000 - K0523 + 000

Albay 2nd DEO, Region V

2025₱18.1M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/CONCRETING OF IRRIGATION SERVICE ROADS IN CAVASI-TINAMPO (LIGAO CITY SECTION) - BONGORAN-OBALIW RINAS (OAS ALBAY SECTION), OAS, ALBAY

Albay 3rd DEO, Region V

2020₱15.6M
Past target date (DPWH On-Going)
View all 50 projects →

4. Implementation

Contract Amount

₱4,837,968.00

Progress

Reported complete (DPWH)

Start Date

June 26, 2019

Target End

October 23, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)AlbayManitoCabacongan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-11-03El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.