Roads20L00150

REHABILITATION OF PAVED ROAD ALONG BYPASS RD. AT JCT. DAVAO - COTABATO RD. - CENTRAL PARK (CORDILLERA RD.) - JCT. MATINA APLAYA RD., DAVAO CITY

REHABILITATION OF PAVED ROAD ALONG BYPASS RD. AT JCT. DAVAO - COTABATO RD. - CENTRAL PARK (CORDILLERA RD.) - JCT. MATINA APLAYA RD., DAVAO CITY is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱96,499,970.22. Status: Reported complete (DPWH). Contractor on record: RAKKI CORP. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱96,499,970.22

Progress

Reported complete (DPWH)

Start Date

December 22, 2020

Target End

November 8, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.