Buildings and Facilities21IC0035

BUILDING AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - REHAB. OF THE MAIN BUILDING, NEDA REGIONAL OFFICE VIII, PALO, LEYTE

BUILDING AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - REHAB. OF THE MAIN BUILDING, NEDA REGIONAL OFFICE VIII, PALO, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱9,650,000.00. Status: Reported complete (DPWH). Contractor on record: 4ANGLE CONST. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2021 · ₱28,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱9,650,000 · 4ANGLE CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-05-29 → 2021-06-16

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: BUILDING AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - REHAB. OF THE MAIN BUILDING, NEDA REGIONAL OFFICE VIII, PALO, LEYTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱28,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure And Drainage, Barangay Bobonon, Alangalang, Leyte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Leyte 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

CID No. 21IC0035

₱9,650,000.00 · 4ANGLE CONSTRUCTION

Award / contract ref: 21IC0035

Contractor

C

23 projects · ₱230.2M total · 0 flags

4. Implementation

Contract Amount

₱9,650,000.00

Progress

Reported complete (DPWH)

Start Date

March 12, 2021

Target End

July 29, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)LeytePaloBaras
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.