Roads25FF0054

CSSP;BASIC INFRA PROGRAM(BIP)-ACCESS ROADS & OR BRIDGES FROM THE NATIONAL ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING FACILITIES-CONST OF ROADS WITH SLOPE PROTECTION WORKS OF PORO -SAN JOSE EAST -SAN JOSE WEST CANAMAN CAMARINES SUR

CSSP;BASIC INFRA PROGRAM(BIP)-ACCESS ROADS & OR BRIDGES FROM THE NATIONAL ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING FACILITIES-CONST OF ROADS WITH SLOPE PROTECTION WORKS OF PORO -SAN JOSE EAST -SAN JOSE WEST CANAMAN CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 3rd DEO, Region V. Reported contract value: ₱146,420,941.08. Status: Past target date (DPWH On-Going). Contractor on record: CENTERWAYS CONST AND DEVELOPMENT INC. Figures trace to dpwh.

Camarines Sur 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Protection Structure along Hibago River Flood Mitigation Structure, Right Side, Upstream of Hibago River, Barangay Pinit, Ocampo, Camarines Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Camarines Sur 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

309 projects · ₱22.7B total · 8 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM-TIKAS)-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE PROJECTS

Region V, Region V

2024₱263.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-SPECIAL ROAD FUND-MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG JCT. PUTIAO-PILAR-DONSOL ROAD-K0549+000 -K0554+000 PILAR, SORSOGON

Sorsogon DEO, Region V

2024₱242.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CADAC-AN RIVER FLOOD MITIGATION STRUCTURE, BARANGAY GUMAPIA, IROSIN, SORSOGON

Sorsogon 2nd DEO, Region V

2025₱188.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, NAGA CITY, CAMARINES SUR, NAGA CITY, CAMARINES SUR (3RD LEGISLATIVE DISTRI

Region V, Region V

2024₱184.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, INAMIGAN RIVER, BARANGAY PAOLBO,

Region V, Region V

2025₱169.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM(CSSP)-BASIC INFRASTRUCTURE PROGRAM(BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, PRES. CORY AQUINO BOULEVARD EXTENSION, TALISA

Region V, Region V

2023₱153.4M
Reported complete (DPWH)
View all 309 projects →

4. Implementation

Contract Amount

₱146,420,941.08

Progress

Past target date (DPWH On-Going)

Start Date

September 2, 2025

Target End

July 8, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.