Flood Control and Drainage16FE0007No coordinates published by DPWH

CONSTRUCTION/REHABILITATION & IMPROVEMENT OF CALABANGA FLOOD CONTROL (WATERWAYS), BRGY. SABANG-SALVACION BAYBAY-SAN ROQUE-SAN PABLO, CALABANGA, CAMARINES SUR 3RD LD

CONSTRUCTION/REHABILITATION & IMPROVEMENT OF CALABANGA FLOOD CONTROL (WATERWAYS), BRGY. SABANG-SALVACION BAYBAY-SAN ROQUE-SAN PABLO, CALABANGA, CAMARINES SUR 3RD LD is a DPWH-tracked public work in Camarines Sur 3rd DEO, Region V. Reported contract value: ₱37,240,039.12. Status: Reported complete (DPWH). Contractor on record: HGG BUILDERS. Figures trace to dpwh.

Camarines Sur 3rd DEO, Region V

DPWH did not publish coordinates for this project. Location estimated from the project title (barangay level); satellite images may not show the exact site.

Region: Region V

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2016 · ₱40,000

    Probable match · score 0.89

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROV-16-0027986 · ₱243,341 · release to the district office, not itemized per project

    Possible match · score 0.65

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱37,240,039 · HGG BUILDERS AND SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-09-27 → 2022-12-06

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/REHABILITATION & IMPROVEMENT OF CALABANGA FLOOD CONTROL (WATERWAYS), BRGY. SABANG-SALVACION BAYBAY-SAN ROQUE-SAN PABLO, CALABANGA, CAMARINES SUR 3RD LD

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation and Improvement of Calabanga Flood Control (Waterways), Brgy. Sabang - Salvacion Baybay - San Roque - San Pablo, Calabanga, Camarines Sur 3rd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-16-0027986

₱243,341.00 · FY2016

Released to Division of Sorsogon (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

16FE0007

₱37,240,039.12 · HGG BUILDERS AND SUPPLY

Award / contract ref: 16FE0007

Contractor

C

233 projects · ₱17.1B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENTRESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG ESTRELLA, STA. 000+000-STA. 000+616.85, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱277.2M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, (UPSTREAM), BRGY. MULAWIN-BRGY. DEL PILAR, NAUJAN,

Region IV-B, Region IV-B

2025₱276.0M
Past target date (DPWH On-Going)
No sat.

CLUSTER 22: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- REHAB. OF ROAD WITH SLIPS, SLOPE CIOLLAPSE AND LANDSLIDE ALONG TAYTAY-BANTULAN-STA. CRUZ PORT ROAD, 22.1: STA. 1+026-STA. 1+161 (R/S); 22.2: STA. 1+057-STA. 1+164 (L/S); 22.3: STA.

Region IV-B, Region IV-B

2022₱252.4M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, POBLACION SAWANG, RIGHT SIDE PHASE 1, LOBOC,

Region VII, Region VII

2024₱241.2M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF MOGPOG SHORE PROTECTION/BOULEVARD, MOGPOG, MARINDUQUE

Region IV-B, Region IV-B

2024₱241.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF LIPA-MATAAS NA KAHOY ROAD INCLUDING URBAN DRAINAGE DEVELOPMENT AND ROAD SAFETY DEVICES, BATANGAS

Region IV-A, Region IV-A

2023₱241.2M
Past target date (DPWH On-Going)
View all 233 projects →

4. Implementation

Contract Amount

₱37,240,039.12

Progress

Reported complete (DPWH)

Start Date

February 15, 2016

Target End

August 30, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)Camarines SurCalabanga
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.