Unprogrammed Appropriations 202424RG0138

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CONCRETE ROAD-JCT. DUMAGUETE

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CONCRETE ROAD-JCT. DUMAGUETE is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱33,723,098.95. Status: Past target date (DPWH On-Going). Contractor on record: KOUKEN CONST 26573. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱19,350,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Tinaogan, Bindoy, Negros Oriental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Negros Oriental 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 26573

107 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DUMAGUETE NORTH RD (JCT BAIS-KABANKALAN-NEGROS OCC BDRY) - K0118 + 400 - K0120 + 300, GUIHULNGAN CITY, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2025₱106.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING ALONG PRIMARY ROAD-DUMAGUETE NORTH ROAD (JCT. BAIS-KABANKALAN-NEGROS OCC BDRY) K0114+194 - K0116+580, GUIHULNGAN CITY, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2025₱101.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM/NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DUMAGUETE NORTH RD (JCT BAIS - KABANKALAN - NEGROS OCC BDRY) - K0104 + 828 - K0107 + 303, LA LIBERTAD, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2023₱94.6M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DUMAGUETE NORTH RD (JCT BAIS - KABANKALAN - NEGROS OCC BDRY) - K110+000 - K112+480, GUIHULNGAN CITY

Negros Oriental 1st DEO, Negros Island Region

2024₱71.1M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DUMAGUETE NORTH RD (JCT BAIS - KABANKALAN - NEGROS OCC BDRY) - K0107 + 875 -K0109+754, K0109+792-K0110+000, LA LIBERTAD, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2024₱68.0M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - IMPROVEMENT OF ROADS, BARANGAY NASUNGGAN - AYA ROAD, LA LIBERTAD, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2024₱48.5M
Reported complete (DPWH)
View all 107 projects →

4. Implementation

Contract Amount

₱33,723,098.95

Progress

Past target date (DPWH On-Going)

Start Date

June 5, 2025

Target End

October 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.