Buildings and Facilities17IC0135

CLUSTER 21: 1.&2.) CONST. OF SINGLE STY. SCIENCE LAB. BLDG. (7MX18M), BLDG. A - P 2,875,120.51 & BLDG. B - P2,875,120.51 AND 3.&4.) CONST. OF SINGLE STY. COMP. (ICT) LAB. BLDG. (7MX18M), BLDG. A - P 2,875,120.51 & BLDG. B - P 2,875,120.51, PALO, NATIONAL

CLUSTER 21: 1.&2.) CONST. OF SINGLE STY. SCIENCE LAB. BLDG. (7MX18M), BLDG. A - P 2,875,120.51 & BLDG. B - P2,875,120.51 AND 3.&4.) CONST. OF SINGLE STY. COMP. (ICT) LAB. BLDG. (7MX18M), BLDG. A - P 2,875,120.51 & BLDG. B - P 2,875,120.51, PALO, NATIONAL is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱11,440,783.27. Status: Reported complete (DPWH). Contractor on record: JULITA BUILDERS. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Bangon River, Palo, Leyte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0005022

₱10,000,000.00 · FY2017

Released to Camarines Sur 3rd Re District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱11,440,783.27

Progress

Reported complete (DPWH)

Start Date

January 18, 2018

Target End

September 14, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.