Roads18JD0102

CONSTRUCTION OF SUNRISE BOULEVARD PHASE III, DAPITAN CITY, ZAMBOANGA DEL NORTE

CONSTRUCTION OF SUNRISE BOULEVARD PHASE III, DAPITAN CITY, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 1st DEO, Region IX. Reported contract value: ₱19,299,708.09. Status: Reported complete (DPWH). Contractor on record: WESTMIN ENT. Figures trace to dpwh.

Zamboanga del Norte 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control structure at Dapitan City Sunrise Boulevard/River Bank Protection, including RROW Dapitan City, Zamboanga del Norte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIX-18-0014811

₱372,892.00 · FY2018

Released to (Zamboanga Regional Science High 2018 School) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,299,708.09

Progress

Reported complete (DPWH)

Start Date

March 28, 2019

Target End

July 25, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.