Buildings and Facilities19BH0044

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING-SANTIAGO CITY

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING-SANTIAGO CITY is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱40,689,000.00. Status: Reported complete (DPWH). Contractor on record: NTL BUILDERS AND DEVELOPER. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

179 projects · ₱4.0B total · 0 flags

4. Implementation

Contract Amount

₱40,689,000.00

Progress

Reported complete (DPWH)

Start Date

September 26, 2019

Target End

June 29, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.