Buildings and Facilities19ID0024

CONSTRUCTION OF MULTI-PURPOSE BUILDING(COVERED COURT),BRGY. MACOPA,JARO,LEYTE

CONSTRUCTION OF MULTI-PURPOSE BUILDING(COVERED COURT),BRGY. MACOPA,JARO,LEYTE is a DPWH-tracked public work in Leyte 2nd DEO, Region VIII. Reported contract value: ₱1,962,576.00. Status: Reported complete (DPWH). Contractor on record: EXCEL C'S BUILDERS. Figures trace to dpwh.

Leyte 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,962,576.00

Progress

Reported complete (DPWH)

Start Date

August 14, 2019

Target End

October 22, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.