Roads25CP0088

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD AT BARANGAY BAYABAS, DONA REMEDIOS TRINIDAD, BULACAN

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD AT BARANGAY BAYABAS, DONA REMEDIOS TRINIDAD, BULACAN is a DPWH-tracked public work in Bulacan 3rd DEO, Region III. Reported contract value: ₱118,940,309.38. Status: Past target date (DPWH On-Going). Contractor on record: 11-16 CONST. Figures trace to dpwh.

Bulacan 3rd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Catulinan, Baliuag, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

244 projects · ₱19.8B total · 8 flags

4. Implementation

Contract Amount

₱118,940,309.38

Progress

Past target date (DPWH On-Going)

Start Date

March 31, 2025

Target End

October 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.