Buildings and Facilities17D00061

CONSTRUCTION OF EVACUATION CENTER AT MULANAY, QUEZON PROVINCE

CONSTRUCTION OF EVACUATION CENTER AT MULANAY, QUEZON PROVINCE is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱34,738,116.59. Status: Reported complete (DPWH). Contractor on record: PROTECH CONST. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

68 projects · ₱2.0B total · 0 flags

Other projects by this contractor

No sat.

FY 2020 DPWH INFRASTRUCTURE PROJECTS, CONVERGENCE & SPECIAL SUPPORT PROGRAM, CONST./IMPVT. OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY, CONSTRUCTION OF ADMINISTRATION BUILDING HEADQUARTERS, CAMP GUILLERMO NAKAR, LUCENA CITY, QUEZON

Region IV-A, Region IV-A

2020₱113.9M
Past target date (DPWH On-Going)
No sat.

DORMITORY FOR GRADUATE STUDENTS,UP LOS BAÑOS, LAGUNA

Region IV-A, Region IV-A

2018₱96.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ADMINISTRATION BUILDING, HEADQUARTERS, CAMP GUILLERMO NAKAR, LUCENA CITY, QUEZON, PHASE VI

Region IV-A, Region IV-A

2025₱94.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS- SECONDARY ROADS - STA ROSA- ULAT-TAGAYTAY RD. K0061 + (-020) - K0061 + 297 AND STA

Cavite 3rd DEO, Region IV-A

2021₱68.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CARAMORAN POBLACION BYPASS RO

Region V, Region V

2023₱57.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-NEW BAHI BR. (B02809LZ) ALONG DAANG MAHARLIKA (LZ), LUPI, CAMARINES SUR (1ST LEGISLATIVE DISTRICT)

Region V, Region V

2023₱55.4M
Past target date (DPWH On-Going)
View all 68 projects →

4. Implementation

Contract Amount

₱34,738,116.59

Progress

Reported complete (DPWH)

Start Date

November 28, 2017

Target End

November 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.