Roads19I00151

REHABILITATION/RECONSTRUCTION OF CIRCUMFERENTIAL ROADS WITH SLIPS, SLOPES COLLAPSED AND LANDSLIDE ALONG BRGY. PINGAN, GEN. MAC ACTHUR, EASTERN SAMAR

REHABILITATION/RECONSTRUCTION OF CIRCUMFERENTIAL ROADS WITH SLIPS, SLOPES COLLAPSED AND LANDSLIDE ALONG BRGY. PINGAN, GEN. MAC ACTHUR, EASTERN SAMAR is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱99,087,953.13. Status: Reported complete (DPWH). Contractor on record: 888 ACY ENT. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

292 projects · ₱9.1B total · 5 flags

4. Implementation

Contract Amount

₱99,087,953.13

Progress

Reported complete (DPWH)

Start Date

February 26, 2020

Target End

May 22, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.