Roads22B00027

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS- ALICIA-ANGADANAN- SAN GUILLERMO-CAUAYAN CITY-NAGUILIAN ALTERNATE ROUTE, PACKAGE 2, ISABELA

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS- ALICIA-ANGADANAN- SAN GUILLERMO-CAUAYAN CITY-NAGUILIAN ALTERNATE ROUTE, PACKAGE 2, ISABELA is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱28,901,823.63. Status: Reported complete (DPWH). Contractor on record: CAMBERWELL CONST AND SUPPLIES. Figures trace to dpwh.

Region II, Region II
Region: Region II

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 22B00027 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-05-24 → 2025-06-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS- ALICIA-ANGADANAN- SAN GUILLERMO-CAUAYAN CITY-NAGUILIAN ALTERNATE ROUTE, PACKAGE 2, ISABELA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

237 projects · ₱3.3B total · 5 flags

Other projects by this contractor

Construction of Bongabong River Control, Brgy. Morente Section, Bongabong, Oriental Mindoro

BONGABONG (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱96.5M
Reported complete (DPWH)

Construction of Cagayan River Flood Control Project, Barangay Furao, Gamu, Isabela

GAMU (ISABELA), ISABELA, Region II

2024₱96.5M
Reported complete (DPWH)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF PINACANAUAN RIVER FLOOD CONTROL STRUCTURE, BRGY. DICAMAY,

Isabela 3rd DEO, Region II

2025₱96.4M
Reported complete (100% progress, DPWH status On-Going)

Construction of Cagayan River Flood Control Project, Barangay Magsaysay, Naguilian, Isabela, Phase II

SAN MARIANO (ISABELA), ISABELA, Region II

2024₱96.4M
Reported complete (DPWH)

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT BARANGAY PALATTAO (CONTINUATION), NAGUILIAN

Isabela 3rd DEO, Region II

2025₱96.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCES ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - ACCESS ROAD LEADING TO PALANAN AIRPORT, PALANAN, ISABELA

Isabela 3rd DEO, Region II

2021₱96.3M
Reported complete (DPWH)
View all 237 projects →

4. Implementation

Contract Amount

₱28,901,823.63

Progress

Reported complete (DPWH)

Start Date

March 21, 2022

Target End

December 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region II (Cagayan Valley)IsabelaSan Guillermo
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.