Flood Control and Drainage17CF0089No coordinates published by DPWH

CONSTRUCTION/MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CORONEL RIVER, CALABASA STA. 22+326.22 - STA. 22+515.22, GABALDON, NUEVA ECIJA

CONSTRUCTION/MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CORONEL RIVER, CALABASA STA. 22+326.22 - STA. 22+515.22, GABALDON, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱7,883,329.38. Status: Reported complete (DPWH). Contractor on record: CCF EARTHMOVING CORP. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III

DPWH did not publish coordinates for this project. Location estimated from the project title (barangay level); satellite images may not show the exact site.

Region: Region III

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱8,336

    Probable match · score 0.90

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXI-17-0015657 · ₱32,557 · release to the district office, not itemized per project

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17CF0089 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-02-10 → 2025-04-30

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CORONEL RIVER, CALABASA STA. 22+326.22 - STA. 22+515.22, GABALDON, NUEVA ECIJA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱8,336,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Coronel River, Calabasa, Sta. 20+898.25-Sta. 20+981.30, Gabaldon, Nueva Ecija
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0015657

₱32,557.00 · FY2017

Released to Tagakpan National Mo High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

88 projects · ₱665.6M total · 0 flags

Other projects by this contractor

View all 88 projects →

4. Implementation

Contract Amount

₱7,883,329.38

Progress

Reported complete (DPWH)

Start Date

July 21, 2017

Target End

October 12, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)Nueva EcijaGabaldon
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
LandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.