Roads25PG0020

LUBUONG-BOKIAWAN-NUNGULUNAN ROAD LEADING TO BAKUNG SPIDER WEB AND OTHER TOURISM DESTINATIONS, HUNGDUAN, IFUGAO

LUBUONG-BOKIAWAN-NUNGULUNAN ROAD LEADING TO BAKUNG SPIDER WEB AND OTHER TOURISM DESTINATIONS, HUNGDUAN, IFUGAO is a DPWH-tracked public work in Ifugao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱9,674,224.24. Status: Past target date (DPWH On-Going). Contractor on record: ALFALFA CONST. Figures trace to dpwh.

Ifugao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Poblacion Pakawit Communal Irrigation System (CIS), Tinoc, Ifugao
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ifugao 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

44 projects · ₱2.2B total · 0 flags

Other projects by this contractor

No sat.

ROAD UPGRADING (UNPAVED TO PAVED) ACOP - KAPANGAN - KIBUNGAN - BAKUN ROAD K0320+771

Cordillera Administrative Region, Cordillera Administrative Region

2016₱146.2M
Reported complete (DPWH)
No sat.

RD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL RD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED RD STDS (HDM-4 PROJECT ANALYSIS), BANAUE-MAYOYAO-A.LISTA-ISABELA BDRY ROAD, K0349+948 - K0350+038, K0352+226 - K0352+503, K0364+753 - K0364+801, K0377+

Cordillera Administrative Region, Cordillera Administrative Region

2016₱146.2M
Reported complete (DPWH)
No sat.

RD UPGRADNG (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED RD STDS (HDM-4 ANALYSIS) CLAVERIA - CALANASAN - KABUGAO ROAD, K0653+541-K0655+420, K0656+935-K0657+702,K0657+720-K0658+343

Cordillera Administrative Region, Cordillera Administrative Region

2016₱144.8M
Reported complete (DPWH)
No sat.

RD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL RD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED RD STDS (HDM-4 PROJ ANALYSIS), BANAUE-MAYOYAO-A.LISTA-ISABELA RD, K0386+328 - K0388+581, K0388+581 - K0389+663, K0389+757 - K0391+066, K0391+197 - K039

Cordillera Administrative Region, Cordillera Administrative Region

2016₱141.0M
Reported complete (DPWH)
No sat.

RD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL RD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED RD STDS (HDM-4 PROJ ANALYSIS) KIANGAN - TINOC - BUGUIAS ROAD, CHAINAGE 25277 - CHAINAGE 25393, CHAINAGE 35707 - CHAINAGE 39337

Cordillera Administrative Region, Cordillera Administrative Region

2016₱140.1M
Past target date (DPWH On-Going)
No sat.

RD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL RD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED RD STDS (HDM-4 PROJ ANALYSIS), UBAO-TAANG ROAD K0408+314 - K0412+064

Cordillera Administrative Region, Cordillera Administrative Region

2016₱140.0M
Past target date (DPWH On-Going)
View all 44 projects →

4. Implementation

Contract Amount

₱9,674,224.24

Progress

Past target date (DPWH On-Going)

Start Date

March 24, 2025

Target End

September 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.