Buildings and Facilities21HN0047

LP: LOCAL INFRASTRUCTURE PROGRAM -BUILDINGS AND OTHER STRUCTURES -MULTIPURPOSE/FACILITIES -CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ALEGRIA, CORDOVA, CEBU

LP: LOCAL INFRASTRUCTURE PROGRAM -BUILDINGS AND OTHER STRUCTURES -MULTIPURPOSE/FACILITIES -CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ALEGRIA, CORDOVA, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱2,880,905.86. Status: Reported complete (DPWH). Contractor on record: GREEN WORLD CONST. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2021 · ₱1,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 21HN0047 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-03-17 → 2026-02-04

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: LP: LOCAL INFRASTRUCTURE PROGRAM -BUILDINGS AND OTHER STRUCTURES -MULTIPURPOSE/FACILITIES -CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ALEGRIA, CORDOVA, CEBU

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱1,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage System, Barangay Tilhaong, Consolacion, Cebu
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Cebu 6th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

45 projects · ₱594.8M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS, WATER SUPPLY SYSTEMS: CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, DUMANJUG, CEBU

Cebu 7th DEO, Region VII

2023₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT PUROK MAIS-PUROK NANGKA (PACKAGE

Cebu 7th DEO, Region VII

2024₱94.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT PUROK MAIS - PUROK NANGKA, BARAN

Cebu 7th DEO, Region VII

2024₱70.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL ALONG LALAO RIVER (UPSTREAM), MALABUYOC, CEBU

Cebu 7th DEO, Region VII

2025₱56.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF LOON - CABILAO WATERWORKS, LOON, BOHOL

Bohol 1st DEO, Region VII

2023₱48.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM: CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, WATER MANAGEMENT FACILITIES/WATER SUPPLY, CONSTRUCTION OF WATER SUPPLY PROJECT, ARGAO, CEBU

Cebu 2nd DEO, Region VII

2018₱41.0M
Reported complete (DPWH)
View all 45 projects →

4. Implementation

Contract Amount

₱2,880,905.86

Progress

Reported complete (DPWH)

Start Date

February 17, 2021

Target End

May 17, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)CebuCordovaAlegria
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.