Roads25A00163

CONSTRUCTION OF MISSING LINKS/ NEW ROADS, MANGATAREM -STA CRUZ ROAD, PANGASINAN

CONSTRUCTION OF MISSING LINKS/ NEW ROADS, MANGATAREM -STA CRUZ ROAD, PANGASINAN is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱56,163,196.19. Status: Past target date (DPWH On-Going). Contractor on record: BERSON'S CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱56,163,196.19

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2025

Target End

October 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.