Roads21AG0120

ROAD CONCRETING, BARANGAY VICTORY, BOLINAO, PANGASINAN

ROAD CONCRETING, BARANGAY VICTORY, BOLINAO, PANGASINAN is a DPWH-tracked public work in Pangasinan 1st DEO, Region I. Reported contract value: ₱15,047,708.00. Status: Reported complete (DPWH). Contractor on record: RAMDC CONST AND TRADING. Figures trace to dpwh.

Pangasinan 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation/Improvement of Flood Control Structure/Protection Dike, Barangay Legaspi, Tayug, Pangasinan
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Pangasinan 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

119 projects · ₱1.5B total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURES IN BALINCAGUING RIVER (BANGAN-ODA SECTION II), BRGY. BANGAN ODA, AGNO, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱94.6M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROGRAM ALLEVIATING GAPS(SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BRIDGE CONNECTING SANTIAGO ISLAND TO BOLINAO(PACKAGEB)BOLINAO,PANGASINAN

Pangasinan 1st DEO, Region I

2024₱94.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-ROAD WIDENING-BANI-AGNO RD(KO342+790-KO345+300) AT AGNO, PANGASINAN

Pangasinan 1st DEO, Region I

2019₱77.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO LUCAP BOULEVARD AND MANGROVE PARK, BRGY. BUED, ALAMINOS CITY, PANGASINAN PACKAGE II

Pangasinan 1st DEO, Region I

2023₱53.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO LUCAP BOULEVARD AND MANGROVE PARK, BRGY. BUED, ALAMINOS CITY, PANGASINAN PACKAGE III

Pangasinan 1st DEO, Region I

2023₱53.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO LUCAP BOULEVARD AND MANGROVE PARK, BRGY. BUED, ALAMINOS CITY, PANGASINAN PACKAGE IV

Pangasinan 1st DEO, Region I

2023₱48.2M
Reported complete (DPWH)
View all 119 projects →

4. Implementation

Contract Amount

₱15,047,708.00

Progress

Reported complete (DPWH)

Start Date

March 3, 2021

Target End

June 15, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.