Buildings and Facilities19CE0046

CONSTRUCTION OF MULTI-PURPOSE BUILDING, MALIGAYA, RIZAL, NUEVA ECIJA

CONSTRUCTION OF MULTI-PURPOSE BUILDING, MALIGAYA, RIZAL, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱2,397,247.38. Status: Reported complete (DPWH). Contractor on record: WIZARD CONCRETE SOLUTIONS AND CONST CORP FORMERLY: WIZARD TRADING. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    SARO SARO-BMB-F-19-0010558 · ₱153,529 · release to the district office, not itemized per project

    Possible match · score 0.64

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19CE0046 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-11-14 → 2022-02-17

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING, MALIGAYA, RIZAL, NUEVA ECIJA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-F-19-0010558

₱153,529.00 · FY2019

Released to MSU-Tawi-Tawi College of Ms Technology and Oceanography (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

210 projects · ₱5.3B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD, MERCED

Region V, Region V

2024₱144.6M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-PRIMARY ROADS, BALER-DAANG MAHARLIKA (LZ), PROVINCE OF NUEVA ECIJA

Region III, Region III

2021₱101.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-TERTIARY ROADS, PANTABANGAN-CANILI-BASAL-BALER ROAD, PROVINCE OF NUEVA ECIJA

Region III, Region III

2021₱98.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF P-5 BORABOD TO AWITAN ROAD, DA

Region V, Region V

2023₱96.5M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT PALESTINA, SAN JOSE CITY, NUEVA ECIJA

Nueva Ecija 1st DEO, Region III

2019₱96.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT PINAGPANAAN - RIZAL - PANTABANGAN RD K0166+005 - K0166+662, K0135+551.60 - K0135+628, K0137+000 - K0137+386, K0143+304 - K0143+438, K0149+000 - K0149+427, K0149+442 - K0150+446, K0155+080

Nueva Ecija 1st DEO, Region III

2019₱96.1M
Reported complete (DPWH)
View all 210 projects →

4. Implementation

Contract Amount

₱2,397,247.38

Progress

Reported complete (DPWH)

Start Date

June 11, 2019

Target End

October 8, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)Nueva EcijaRizalMaligaya
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.