Buildings and Facilities22IB0149

CONSTRUCTION OF 1STY2CL, CACATMONAN PRIMARY SCHOOL, HERNANI, EASTERN SAMAR

CONSTRUCTION OF 1STY2CL, CACATMONAN PRIMARY SCHOOL, HERNANI, EASTERN SAMAR is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱6,271,610.02. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: YFL BUILDERS. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cabay Flood Control, Balangkayan, Eastern Samar
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Eastern Samar DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱6,271,610.02

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

January 16, 2023

Target End

October 2, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.