Buildings and Facilities24CA0041

BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF SANTA LUCIA COVERED COURT, SAMAL, BATAAN

BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF SANTA LUCIA COVERED COURT, SAMAL, BATAAN is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱7,268,953.66. Status: Past target date (DPWH On-Going). Contractor on record: P C VALENCIA CONST. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project along Sapang Kastila Capitangan, Bataan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bataan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

33 projects · ₱202.1M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM IMPROVEMENT/ REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG PENTOR-BALSIK RIVER (TORRES SECTION), STA. (-) 2+735 TO STA. (-) 2+931DINALUPIHAN, BATAAN

Bataan 1st DEO, Region III

2019₱19.6M
Reported complete (DPWH)
No sat.

LOCAL INFRASTRUCTURE PROGRAM -FLOOD CONTROL AND DRAINAGE- FLOOD CONTROL STRUCTURES/FACILITIES- CONSTRUCTION/IMPROVEMENT OF FLOOD CONTROL PROJECT FROM CAULAMAN RIVER TO PENTOR-BALSIK RIVER, SAN SIMON SECTION, DINALUPIHAN, BATAAN

Bataan 1st DEO, Region III

2020₱14.7M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - BUILDINGS AND OTHER STRUCTURES - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI - PURPOSE BUILDING (DIALYSIS TREATMENT CENTER)

North Manila DEO, National Capital Region

2019₱12.4M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY STA. LUCIA, ITBAYAT, BATANES

Batanes DEO, Region II

2023₱10.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS/ FACILITIES: CONSTRUCTION OF ROAD, YAS - YAS TO PADANGAN, PHASE I, BARANGAY IHUBOK I, BASCO, BATANES

Batanes DEO, Region II

2025₱9.9M
Past target date (DPWH On-Going)
No sat.

BIP-MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI - PURPOSE BUILDING (BARANGAY HALL), BRGY. SINAKAN, SABTANG, BATANES

Batanes DEO, Region II

2024₱9.9M
Reported complete (100% progress, DPWH status On-Going)
View all 33 projects →

4. Implementation

Contract Amount

₱7,268,953.66

Progress

Past target date (DPWH On-Going)

Start Date

April 2, 2024

Target End

September 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.