Water Provision and Storage22HH0102

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III) - CONSTRUCTION OF WATERWORKS AT BARANGAY CARRETA, CEBU CITY, CEBU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III) - CONSTRUCTION OF WATERWORKS AT BARANGAY CARRETA, CEBU CITY, CEBU is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱4,940,000.00. Status: Reported complete (DPWH). Contractor on record: PLANAC CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Lahug River, Cebu City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Cebu City DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,940,000.00

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

July 21, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.