Roads21MH0110

CONCRETING OF BRGY. SALABACA TO BRGY. LAGUINDING FMR PHASE 2, BRGY. SALABACA AND BRGY. LAGUINDING, ESPERANZA, SULTAN KUDARAT

CONCRETING OF BRGY. SALABACA TO BRGY. LAGUINDING FMR PHASE 2, BRGY. SALABACA AND BRGY. LAGUINDING, ESPERANZA, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 2nd DEO, Region XII. Reported contract value: ₱14,179,399.86. Status: Reported complete (DPWH). Contractor on record: FPJ CONST AND SUPPLY. Figures trace to dpwh.

Sultan Kudarat 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of River Bank Protection / Flood Control at Brgy. Salabaca, Esperanza, Sultan Kudarat
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Sultan Kudarat 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,179,399.86

Progress

Reported complete (DPWH)

Start Date

March 17, 2021

Target End

June 11, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.