Construction of Slope Protection Structure22OB0151

Bank Improvement/Protection along C-6 Open Channel (Phase 1), Taguig City

Bank Improvement/Protection along C-6 Open Channel (Phase 1), Taguig City is a DPWH-tracked public work in TAGUIG CITY (METROPOLITAN MANILA), TAGUIG CITY, National Capital Region. Reported contract value: ₱89,179,369.28. Status: Reported complete (DPWH). Contractor on record: J C UYECIO CONST AND DEVELOPMENT CO / A J LAVA BUILDERS CORP FORMERLY: A J LAVA BUIL. Figures trace to sumbong.

TAGUIG CITY (METROPOLITAN MANILA), TAGUIG CITY, National Capital Region
Region: National Capital Region

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱30,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-A-22-0003018 · ₱90,000,000

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱89,179,369 · J C UYECIO CONST AND DEVELOPMENT CO

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2021-10-29 → 2023-05-07

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: Bank Improvement/Protection along C-6 Open Channel (Phase 1), Taguig City

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along the Banks of Creeks, Brgy. 166 (Phase 2), Caloocan City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003018

₱90,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001634

₱15,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0001871

₱7,396,262.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0005641

₱3,168,112.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003117

₱2,297,896,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0001872

₱687,910.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0009694

₱529,085.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0003215

₱124,316.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0003214

₱1,360,967.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001726

₱202,063,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱89,179,369.28

Progress

Reported complete (DPWH)

Start Date

February 16, 2022

Target End

October 13, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)City of TaguigNapindan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →