Buildings and Facilities24OB0300

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TAÑONG, MARIKINA CITY (PHASE 4)

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TAÑONG, MARIKINA CITY (PHASE 4) is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱38,990,582.80. Status: Reported complete (DPWH). Contractor on record: LTDL BUILDERS. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 200, Barangay 178, Caloocan City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Metro Manila 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

195 projects · ₱2.4B total · 0 flags

4. Implementation

Contract Amount

₱38,990,582.80

Progress

Reported complete (DPWH)

Start Date

April 1, 2024

Target End

January 22, 2025

5. Audit