Flood Control and Drainage16CG0123

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE & DRAINAGE SYSTEM-REHABILITATION OF CHECKGATE @ PALIMPE CENTRO, MASANTOL, PAMPANGA

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE & DRAINAGE SYSTEM-REHABILITATION OF CHECKGATE @ PALIMPE CENTRO, MASANTOL, PAMPANGA is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱7,486,433.00. Status: Reported complete (DPWH). Contractor on record: THREE-IN-ONE CONST. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Projects in Central Luzon - Rehabilitation of Slope Protection along Pampanga River, San Luis, Pampanga
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-16-0014620

₱695,753.00 · FY2016

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

129 projects · ₱1.3B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABACAN RIVER, (PHASE I), MEXICO, PAMPANGA

Pampanga 1st DEO, Region III

2024₱119.0M
Past target date (DPWH On-Going)

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAPANGBALEN RIVER, PHASE I, BARANGAY SAN ILDEFONSO, MAGALANG, PAMPANGA

Pampanga 3rd DEO, Region III

2025₱115.8M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - FLOOD MITIGATION STRUCTURE - CONSTRUCTION/ REHABILITATION OF SLOPE PROTECTION WORKS AT BRGY. MALIWALU, BACOLOR, PAMPANGA

Pampanga 1st DEO, Region III

2025₱91.7M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP): FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION/REHABILITATION OF SAPANG BALEN CREEK, PULUNG BULU SECTION, CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2025₱75.0M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES; IMPROVEMENT/REHABILITATION OF DIKE ALONG ABACAN RIVER (PANDAN BRIDGE TO HENSON BRIDGE) ANGELES CITY, PAMPANGA

Pampanga 3rd DEO, Region III

2024₱72.3M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES: CONSTRUCTION OF SLOPE PROTECTION ALONG LEONCIA CREEK-STO DOMINGO, ANGELES CITY

Pampanga 3rd DEO, Region III

2024₱49.0M
Reported complete (DPWH)
View all 129 projects →

4. Implementation

Contract Amount

₱7,486,433.00

Progress

Reported complete (DPWH)

Start Date

August 4, 2016

Target End

October 17, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.