Buildings and Facilities20KA0117

CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING (WOMEN'S CENTER), CITY HALL COMPOUND, BRGY. CASISANG, MALAYBALAY CITY, BUKIDNON

CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING (WOMEN'S CENTER), CITY HALL COMPOUND, BRGY. CASISANG, MALAYBALAY CITY, BUKIDNON is a DPWH-tracked public work in Bukidnon 1st DEO, Region X. Reported contract value: ₱4,949,877.16. Status: Reported complete (DPWH). Contractor on record: RITCHE-NATHALIE BUILDERS. Figures trace to dpwh.

Bukidnon 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure, Brgy. 1, Malaybalay City, Bukidnon
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Bukidnon 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

47 projects · ₱2.2B total · 0 flags

4. Implementation

Contract Amount

₱4,949,877.16

Progress

Reported complete (DPWH)

Start Date

October 21, 2020

Target End

June 2, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.