Roads17B00013

MFO 1: NATIONAL ROAD NETWORK SERVICES: NETWORK DEVELOPMENT: IMPROVEMENT/WIDENING OF NATIONAL ROADS-ALONG DAANG MAHRLIKA (LZ), K0256+540-K0259+899.20=STA.256+540-STA.260+ 080, K0260+225.70-K0261+090=STA. 260+400-STA. 261+260, BAYOMBONG, NUEVA VIZCAYA

MFO 1: NATIONAL ROAD NETWORK SERVICES: NETWORK DEVELOPMENT: IMPROVEMENT/WIDENING OF NATIONAL ROADS-ALONG DAANG MAHRLIKA (LZ), K0256+540-K0259+899.20=STA.256+540-STA.260+ 080, K0260+225.70-K0261+090=STA. 260+400-STA. 261+260, BAYOMBONG, NUEVA VIZCAYA is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱106,924,739.76. Status: Reported complete (DPWH). Contractor on record: JANN-NORRIS CONST AND SUPPLIES INC FORMELY: JANN-NORRIS CONST AND SUPPLIES. Figures trace to dpwh.

Region II, Region II
Region: Region II

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17B00013 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-04-03 → 2022-06-14

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (widening)

₱12,399,228 per km= 0.4x the Region II median (n=189)

Contract cost ₱106,924,740 ÷ 8.624 km read from the DPWH title (“K0256+540-K0259+899.20; STA.256+540-STA.260+ 080; K0260+225.70-K0261+090; STA. 260+400-STA. 261+260”; K-post / station range length). National percentile: 1. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: MFO 1: NATIONAL ROAD NETWORK SERVICES: NETWORK DEVELOPMENT: IMPROVEMENT/WIDENING OF NATIONAL ROADS-ALONG DAANG MAHRLIKA (LZ), K0256+540-K0259+899.20=STA.256+540-STA.260+ 080, K0260+225.70-K0261+090=STA. 260+400-STA. 261+260, BAYOMBONG, NUEVA VIZCAYA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

247 projects · ₱10.9B total · 0 flags

Other projects by this contractor

No sat.

OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BAYOMBONG-SOLANO BY-PASS ROAD, BAYOMBONG - SOLANO, NUEVA VIZCAYA

Region II, Region II

2019₱238.9M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0292 + 000 - K0293 + 225, K0293 + 356 - K0294 + 100, K0294 + 152 - K

Region II, Region II

2024₱196.4M
Past target date (DPWH On-Going)
No sat.

CAPITAL OUTLAY-NATIONAL BRIDGE CONST'N/REPLACEMENT PROGRAM CONST'N OF MADDIANGAT BRIDGE AND APPROACHES INCLUDING RIGHT-OF-WAY ACQUISITION ALONG BAMBANG KASIBU-QUEZON-SOLANO ROAD, NUEVA VIZCAYA

Region II, Region II

2017₱194.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG MANILA NORTH RD, - K0590+(-784) - K0593+608; K0593+637-K0595+000; K064

Region II, Region II

2024₱184.3M
Past target date (DPWH On-Going)
No sat.

OO 1: ENSURE SAFE AND RELIABLE NAT'L ROAD SYSTEM: NETWORK DEV'T PROGRAM: ROAD WIDENING-PRIMARY ROADS ALONG DAANG MAHARLIKA (LZ),K0254+641-K0255+K249.50, K0259+899.20 - K0260+ 051.7 , K0260+072.30 - K0260+225.70, K0261+090 - K0261+242,QUIRINO LONE DISTRICT

Region II, Region II

2018₱165.2M
Reported complete (DPWH)
No sat.

OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEV'T: ROAD WIDENING PRIMARY ROAD ALONG DAANG MAHARLIKA, K0216+886 K0219+092.70 = STA. 216+781-STA. 219+092.70, K0219+224-K0219+899 = STA. 219+138.70-STA. 219+813.70, STA. FE, NUEVA VIZCAYA

Region II, Region II

2018₱161.1M
Reported complete (DPWH)
View all 247 projects →

4. Implementation

Contract Amount

₱106,924,739.76

Progress

Reported complete (DPWH)

Start Date

February 9, 2017

Target End

November 15, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region II (Cagayan Valley)Nueva VizcayaBayombongBuenavista
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.