Roads21PA0152

REHABILITATION/IMPROVEMENT OF SAN ISIDRO ROAD PHASE II, SAN ISIDRO, ABRA

REHABILITATION/IMPROVEMENT OF SAN ISIDRO ROAD PHASE II, SAN ISIDRO, ABRA is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱47,035,911.70. Status: Reported complete (DPWH). Contractor on record: A D MARRERO GEN CONST. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Patoc Flood Control Phase II, Sta. 0+000 - Sta. 0+500, Bucay, Abra
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Abra DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,035,911.70

Progress

Reported complete (DPWH)

Start Date

January 25, 2022

Target End

June 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.