Flood Control and Drainage16E00030No coordinates published by DPWH

MAG-ASAWANG TUBIG AND ALLIED RIVERS FLOOD MITIGATION/CONTROL PROJECTS, REHAB./CONST. OF GABION REVETMENT AT SAN ANDRES PUTIK, CALAPAN CITY, OR. MINDORO, STA. 0+000 - STA. 0+601.30

MAG-ASAWANG TUBIG AND ALLIED RIVERS FLOOD MITIGATION/CONTROL PROJECTS, REHAB./CONST. OF GABION REVETMENT AT SAN ANDRES PUTIK, CALAPAN CITY, OR. MINDORO, STA. 0+000 - STA. 0+601.30 is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱63,812,177.63. Status: Reported complete (DPWH). Contractor on record: MONOLITHIC CONST. Figures trace to dpwh.

Region IV-B, Region IV-B

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region IV-B

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱63,811,618 · MONOLITHIC CONSTRUCTION AND CONCRETE PRODUCTS, .

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Flood wall / dike / revetment, cost per linear meter (revetment)

₱106,124 per linear m= 0.8x the national median (n=191)

Contract cost ₱63,812,178 ÷ 601.3 linear m read from the DPWH title (“STA. 0+000 - STA. 0+601.30”; station range length (Sta. a+b to c+d)). National percentile: 34. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: MAG-ASAWANG TUBIG AND ALLIED RIVERS FLOOD MITIGATION/CONTROL PROJECTS, REHAB./CONST. OF GABION REVETMENT AT SAN ANDRES PUTIK, CALAPAN CITY, OR. MINDORO, STA. 0+000 - STA. 0+601.30

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

16000000000000000318153997418496

₱63,811,618.35 · MONOLITHIC CONSTRUCTION AND CONCRETE PRODUCTS, .

Award / contract ref: 16000000000000000318153997418496

Contractor

B

299 projects · ₱22.3B total · 0 flags

4. Implementation

Contract Amount

₱63,812,177.63

Progress

Reported complete (DPWH)

Start Date

July 7, 2016

Target End

March 11, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Not yet linked to a PSGC area.
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.