Roads23PC0056

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES-IMPROVEMENT OF BUTAO-PULOT ROAD, CALANASAN, APAYAO

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES-IMPROVEMENT OF BUTAO-PULOT ROAD, CALANASAN, APAYAO is a DPWH-tracked public work in Apayao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱9,497,177.91. Status: Reported complete (DPWH). Contractor on record: ISNAG BUILDERS. Figures trace to dpwh.

Apayao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2023 · ₱15,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23PC0056 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-11-23 → 2023-07-09

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES-IMPROVEMENT OF BUTAO-PULOT ROAD, CALANASAN, APAYAO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Calabigan Flood Control Structure, Barangay Calabigan, Luna, Apayao
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Apayao 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

88 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS - TERTIARY ROADS - APAYAO (CALANASAN) - ILOCOS NORTE RD - (S00644LZ) CHAINAGE 6571 - CHAINAGE 8322

Apayao 2nd DEO, Cordillera Administrative Region

2023₱84.5M
Reported complete (DPWH)
No sat.

CSSP- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS(TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-SAN ISIDRO SUR-POBLACION-LAPPA-MARAG-CADACLAN-SALAGUNTING TOURISM ROAD LEADING TO MANACOTA UNDERGROUND RIVER & OTHER TOURISM

Apayao 2nd DEO, Cordillera Administrative Region

2023₱82.0M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF KARAGAWAN RIVER FLOOD CONTROL, STA. 80+321 - STA. 81+162 (R/S), KARAGAWAN,

Apayao 1st DEO, Cordillera Administrative Region

2024₱74.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT-PAVING OF UNPAVED ROADS-TERTIARY ROADS-CLAVERIA-CALANASAN-KABUGAO RD-K0712+000-K0712+144, K0712+228-713+383 - AT SPECIFIC LOCATIONS ALONG CLAVERIA-CALANASAN-KABUGAO RD (S00631LZ)

Apayao 2nd DEO, Cordillera Administrative Region

2022₱67.6M
Reported complete (DPWH)
No sat.

CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION/IMPROVEMENT OF CALABIGAN-CAGANDUNGAN ROAD, BRGY CAGANDUNGAN & BRGY CALABIGAN, LUNA, APAYAO

Apayao 2nd DEO, Cordillera Administrative Region

2025₱66.1M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM PAVING OF UNPAVED ROADS - TERTIARY ROADS CLAVERIA-CALANASAN-KABUGAO ROAD K0710+539 - K0711+061, K0711+126 - K0711+868

Apayao 2nd DEO, Cordillera Administrative Region

2022₱62.0M
Reported complete (DPWH)
View all 88 projects →

4. Implementation

Contract Amount

₱9,497,177.91

Progress

Reported complete (DPWH)

Start Date

April 5, 2023

Target End

January 20, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Cordillera Administrative Region (CAR)ApayaoCalanasanButao
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
LandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.