Buildings and Facilities17DF0100

CONSTRUCTION OF 4STY 8CL AND 2STY 4CL SCHOOL BUILDING AT TALON NATIONAL HIGH SCHOOL AND CONSTRUCTION OF 2STY 4CL SCHOOL BUILDING AT HALANG BANAYBANAY NHS, AMADEO

CONSTRUCTION OF 4STY 8CL AND 2STY 4CL SCHOOL BUILDING AT TALON NATIONAL HIGH SCHOOL AND CONSTRUCTION OF 2STY 4CL SCHOOL BUILDING AT HALANG BANAYBANAY NHS, AMADEO is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱35,001,480.84. Status: Reported complete (DPWH). Contractor on record: D V SALUD CONST. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱12,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROV-17-0009159 · ₱86,116 · release to the district office, not itemized per project

    Possible match · score 0.65

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱31,020,660 · ALMAKAR BUILDERS & METAL WORKS

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2013-03-27 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF 4STY 8CL AND 2STY 4CL SCHOOL BUILDING AT TALON NATIONAL HIGH SCHOOL AND CONSTRUCTION OF 2STY 4CL SCHOOL BUILDING AT HALANG BANAYBANAY NHS, AMADEO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures and other improvements, including removal of informal settlers along Zapote River Barangay Molino 7, Bacoor City, Cavite
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0009159

₱86,116.00 · FY2017

Released to Division of Camarines Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

17DF0093

₱31,020,660.18 · ALMAKAR BUILDERS & METAL WORKS

Award / contract ref: 17DF0093

Confirmed (exact contract ID) · 100%

17DF0095

₱31,253,400.65 · HAUSLAND CONSTRUCTION

Award / contract ref: 17DF0095

Confirmed (exact contract ID) · 100%

17DF0097

₱31,140,220.88 · BAQPRINCE CONSTRUCTION

Award / contract ref: 17DF0097

Confirmed (exact contract ID) · 100%

17DF0100

₱34,294,458.28 · D.V. SALUD CONSTRUCTION

Award / contract ref: 17DF0100

Confirmed (exact contract ID) · 100%

17DF0098

₱33,424,449.58 · BAQPRINCE CONSTRUCTION

Award / contract ref: 17DF0098

Confirmed (exact contract ID) · 100%

17DF0092

₱30,844,452.10 · D.V. SALUD CONSTRUCTION

Award / contract ref: 17DF0092

Confirmed (exact contract ID) · 100%

17DF0099

₱34,060,791.32 · BAQPRINCE CONSTRUCTION

Award / contract ref: 17DF0099

Contractor

B

21 projects · ₱706.4M total · 0 flags

4. Implementation

Contract Amount

₱35,001,480.84

Progress

Reported complete (DPWH)

Start Date

November 22, 2017

Target End

June 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)CaviteAmadeoTalon
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.