GAA 2024 SSP24P00082

REPAIR/RESTORATION OF INFRASTRUCTURES WHICH WERE DAMAGED BY SEVERE TROPICAL STORM CARINA AND ENHANCED SOUTHWEST MONSOON, KENNON ROAD, K0227+050 - K0227+075, TUBA, BENGUET

REPAIR/RESTORATION OF INFRASTRUCTURES WHICH WERE DAMAGED BY SEVERE TROPICAL STORM CARINA AND ENHANCED SOUTHWEST MONSOON, KENNON ROAD, K0227+050 - K0227+075, TUBA, BENGUET is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱19,300,000.00. Status: Past target date (DPWH On-Going). Contractor on record: TATUM CONST. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱19,300,000.00

Progress

Past target date (DPWH On-Going)

Start Date

December 16, 2024

Target End

March 30, 2025

5. Audit