Roads20OG0044

IMPROVEMENT OF ROADS, AT BARANGAY SANTOL, QUEZON CITY

IMPROVEMENT OF ROADS, AT BARANGAY SANTOL, QUEZON CITY is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱13,948,110.23. Status: Reported complete (DPWH). Contractor on record: UNIMASTERS CONGLOMERATION INC. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2020 · ₱10,000 (shared by many projects, not this project's own line)

    Possible match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20OG0044 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-02-29 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: IMPROVEMENT OF ROADS, AT BARANGAY SANTOL, QUEZON CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Kimo Village, Barangay Sauyo, Quezon City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Quezon City 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

50 projects · ₱2.3B total · 0 flags

Other projects by this contractor

No sat.

ROAD WIDENING - PRIMARY ROADS - PALO - CARIGARA - ORMOC ROAD - KO975+061 - KO975+788, KO975+832.20 - KO980+372, KO982+186 - KO983+255, KO940+454 - KO940+895, LEYTE 2ND LD

Region VIII, Region VIII

2018₱165.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASSES ROAD, INCLUDING ROW NRJ DAANG MAHARLIKA, TAGUIBO-MASAO PORT, (CABCABON-BANZA SECTION), BUTUAN CITY, AGUSAN DEL NORTE 1ST LD., BUTUAN CITY, AGUSAN DEL NORTE 1ST LD.

Region XIII, Region XIII

2016₱140.3M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - PALO - CARIGARA - ORMOC RD. - K0953+466 - K0954+288, K0954+299 - K0955+000, K0955+000 - K0955+344, K0955+357 - K0956+233, CARIGARA, LEYTE 2ND LD

Region VIII, Region VIII

2020₱122.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, SAN FRANCISCO (NRJ HUBANG - STA. ANA - SAN ISIDRO) BYPASS ROAD (DAANG MAHARLIKA ALTERNATE ROUTE), INCLUDING ROW AND BRIDGE, SAN FRANCISCO, AGUSAN DEL SUR

Region XIII, Region XIII

2018₱119.8M
Reported complete (DPWH)
No sat.

IMPROVEMENT/WIDENING OF NATIONAL ROADS, DAANG MAHARLIKA (SURIGAO-AGUSAN SECT.), K1197+550-K1199+289.40, K1202+000-K1202+812.46, K1202+911.75-K1203+238, AGUSAN DEL NORTE

Region XIII, Region XIII

2017₱102.3M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF DIKE WITH CONCRETE REVETMENT ALONG PANDANON - MAGALLANES ROAD, AGUSAN DEL NORTE

Agusan del Norte DEO, Region XIII

2020₱96.5M
Reported complete (DPWH)
View all 50 projects →

4. Implementation

Contract Amount

₱13,948,110.23

Progress

Reported complete (DPWH)

Start Date

November 27, 2020

Target End

July 24, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)Quezon CitySantol
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.