Roads25OF0079

PREVENTIVE MAINTENANCE - SECONDARY ROADS - GEN LUIS ST - K0019 + (-615) - K0019 + 500, QUEZON CITY

PREVENTIVE MAINTENANCE - SECONDARY ROADS - GEN LUIS ST - K0019 + (-615) - K0019 + 500, QUEZON CITY is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱39,039,336.72. Status: Past target date (DPWH On-Going). Contractor on record: EBUILDERS CONST & DEVELOPMENT CORP. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay Baesa, Quezon City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon City 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱39,039,336.72

Progress

Past target date (DPWH On-Going)

Start Date

March 3, 2025

Target End

August 12, 2025

5. Audit