Roads25CC0488

GUIGUINTO BYPASS RD (SANTA RITA-KABILANG BAKOD-CUTCUT RD), PACKAGE 1, STA. 0+620.00 TO STA. 0.+979.37, GUIGUINTO, BULACAN

GUIGUINTO BYPASS RD (SANTA RITA-KABILANG BAKOD-CUTCUT RD), PACKAGE 1, STA. 0+620.00 TO STA. 0.+979.37, GUIGUINTO, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱92,658,491.40. Status: Ongoing (DPWH-reported) (Not Yet Started (DPWH-reported)). Contractor on record: ORANI CONST AND SUPPLY CORP FORMERLY:ORANI BUILDERS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Pinagbarilan, Baliuag, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱92,658,491.40

Progress

Not Yet Started (DPWH-reported)

Start Date

Data not yet available

Target End

December 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.