GAA 2016 MFO-316C00068

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORT AND DECLARED TOURISM-TO DECLARED TOURISM DESTINATIONS-UPGRADING OF DAMPAY SALAZA ACCESS ROAD LEADING TO MOUNT TAPULAO ECO TOURISM PROJECT, PALAUIG, ZAMBALES 2ND LEGISLATIVE DISTRICT

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORT AND DECLARED TOURISM-TO DECLARED TOURISM DESTINATIONS-UPGRADING OF DAMPAY SALAZA ACCESS ROAD LEADING TO MOUNT TAPULAO ECO TOURISM PROJECT, PALAUIG, ZAMBALES 2ND LEGISLATIVE DISTRICT is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱117,238,434.78. Status: Reported complete (DPWH). Contractor on record: HAIDEE CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Region III, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

29 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES STRUCTURAL AND RESILIENCE PROGRAM - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CONVENTION CENTER) INCLUDING SITE DEVELOPMENT, SAN FERNAND

Pampanga 1st DEO, Region III

2024₱187.2M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS, CAPAS-BOTOLAN ROAD (PACKAGE 2), PROVINCE OF ZAMBALES

Region III, Region III

2019₱142.7M
Reported complete (DPWH)
No sat.

CONST AND MAINT OF BRIDGES ALONG NATL ROADS WIDENING OF PERMANENT BRIDGES, INCL ROW TO MORE THAN 2 L

Region III, Region III

2017₱122.5M
Reported complete (DPWH)
No sat.

LOCAL INFRASTRUCTURE PROGRAM: BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/ FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (CONVENTION CENTER), PHASE II, CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2020₱95.0M
Reported complete (DPWH)

LAHAR CONTROL WORKS IN PASIG-POTRERO/GUGU RIVER STA. 0+188-STA. 2+100 GUGU RIVER STA. 2+300-STA.2+700 MINALIN TAIL DIKE, STA. 2+125.24-STA. 0+715 WEST MEGA DIKE, BACOLOR, PAMPANGA

Flood Control Management Cluster, Central Office

2017₱95.0M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CONVENTION CENTER) INCLUDING SITE DEVELOPMENT, SAN FERNANDO CITY, PAMPANGA

Pampanga 1st DEO, Region III

2023₱93.7M
Reported complete (DPWH)
View all 29 projects →

4. Implementation

Contract Amount

₱117,238,434.78

Progress

Reported complete (DPWH)

Start Date

October 9, 2016

Target End

March 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.