GAA 2016 MFO-115D00090

MFO-1 NAT'L. RD. NETWORK SVCS. ASSET PRES. OF NAT'L. RDS., TERTIARY RDS. QUEZON-ALABA-PEREZ RD., ALA

MFO-1 NAT'L. RD. NETWORK SVCS. ASSET PRES. OF NAT'L. RDS., TERTIARY RDS. QUEZON-ALABA-PEREZ RD., ALA is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱55,575,616.00. Status: Reported complete (DPWH). Contractor on record: RAM BUILDERS. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

130 projects · ₱2.7B total · 0 flags

Other projects by this contractor

No sat.

A. ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 1. ASSET PRESERVATION PROGRAM A. REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE 1. TERTIARY ROADS 1. JCT MSR-OLD ZIGZAG RD - K0

Quezon 4th DEO, Region IV-A

2019₱94.6M
Reported complete (DPWH)
No sat.

I. OPERATIONS A. ORGANIZATIONAL OUTCOME 1. ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 2. NETWORK DEVELOPMENT PROGRAM C. CONSTRUCTION OF MISSING LINKS/ NEW ROADS 3. QUEZON-ALABAT-PEREZ CIRCUMFERENTIAL ROAD, INCL. ROW, QUEZON

Quezon 4th DEO, Region IV-A

2018₱88.9M
Reported complete (DPWH)
No sat.

A. MFO -1 NATIONAL ROAD NETWORK SERVICES 1. ASSET PRESERVATION OF NATIONAL ROADS D. CONSTRUCTION/UPGRADING REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS 2. TERTIARY ROADS B. QUEZON-ALABAT-PEREZ RD - K0001+182-K0001+782, K0020+00-K0020+600, K0030+037-K

Quezon 4th DEO, Region IV-A

2017₱83.7M
Reported complete (DPWH)
No sat.

A. ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 1. ASSET PRESERVATION PROGRAM D. REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE 1. PRIMARY ROADS 1. JCT MSR-OLD ZIGZAG RD - K0153+236 - K0153+25

Quezon 4th DEO, Region IV-A

2020₱78.8M
Reported complete (DPWH)
No sat.

A. MFO -1: NATIONAL ROAD NETWORK SERVICES 2. NETWORK DEVELOPMENT A. IMPROVEMENT/WIDENING OF NATIONAL ROADS 1. PRIMARY ROADS A. ALONG N1 1. DAANG MAHARLIKA (LZ) - K0135+ -732 - K0135+ -332, K0137+000 - K0138+016, K0139+000 - K0139+093, K0139+324 - K0140+2

Quezon 4th DEO, Region IV-A

2017₱76.0M
Reported complete (DPWH)
No sat.

A. ORGANIZATIONAL OUTCOME 1. ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 1. ASSET PRESERVATION PROGRAM A. REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDES 1. TERTIATY ROADS 1. JCT MSR-OLD ZIGZAG RD - JCT. MSR-OLD ZIGZAG

Quezon 4th DEO, Region IV-A

2018₱70.2M
Reported complete (DPWH)
View all 130 projects →

4. Implementation

Contract Amount

₱55,575,616.00

Progress

Reported complete (DPWH)

Start Date

February 10, 2016

Target End

July 8, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.