Water Provision and Storage21KC0097

CONSTRUCTION OF WATER SUPPLY (DEEP WELL) BRGY. DICKLUM, (DPWH COMPOUND), MANOLO FORTICH, BUKIDNON

CONSTRUCTION OF WATER SUPPLY (DEEP WELL) BRGY. DICKLUM, (DPWH COMPOUND), MANOLO FORTICH, BUKIDNON is a DPWH-tracked public work in Bukidnon 3rd DEO, Region X. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: PETRINA CONST. Figures trace to dpwh.

Bukidnon 3rd DEO, Region X
Region: Region X

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2021 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 21KC0097 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2021-08-07 → 2025-07-03

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    CY2023 · other

    Confirmed (exact contract ID) · score 1.00

    COA AAR source ↗

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF WATER SUPPLY (DEEP WELL) BRGY. DICKLUM, (DPWH COMPOUND), MANOLO FORTICH, BUKIDNON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Jct Maradugao-Camp Kibaritan-Dominorog Road (Upstream and Downstream) of Macapantig Bridge with Slope Protection, Kalilangan, Bukidnon
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Bukidnon 3rd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

November 19, 2021

Target End

April 8, 2022

5. Audit

Confirmed (exact contract ID) · 100%

COA observation (CY2023 audit, Par. 18 Delayed/Non-submission of Contracts, Purchase Orders (POs) and supporting documents). DPWH's action-plan response to this observation names Contract ID 21KC0097, p. 344. Excerpt: "21KC0097 April 18, 2022 21KC0052 January 12, 2022 22KC0061 October 04, 2022"

CY2023 · p.344

Connected records

Where this project sits

Place (PSGC)
Region X (Northern Mindanao)BukidnonManolo FortichDiclum
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.