Flood Control and Drainage15EB0269

CONSTRUCTION (COMPLETION) OF FLOOD CONTROL SYSTEM AT BABUY RIVER, BARANGAY TANGKALAN, MAMBURAO, OCC. MINDORO

CONSTRUCTION (COMPLETION) OF FLOOD CONTROL SYSTEM AT BABUY RIVER, BARANGAY TANGKALAN, MAMBURAO, OCC. MINDORO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱9,394,037.20. Status: Reported complete (DPWH). Contractor on record: NEW MINDORENOS LUMBER HARDWARE AND GEN MERCHANDISE. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control System at Babuy River, Barangay Tangkalan, Mamburao, Occidental Mindoro
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0032447

₱50,584.00 · FY2016

Released to Clarencio Calagos Memorial School of Fisheries Ter (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

80 projects · ₱673.4M total · 0 flags

4. Implementation

Contract Amount

₱9,394,037.20

Progress

Reported complete (DPWH)

Start Date

April 1, 2016

Target End

July 21, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.